RCP In The Heights Set

Phase 1- putting up the platforms, for two weeks.

 

Phase 2- we will put up the vacuform, where appropriate, and paint the platforms so that the auditorium can be used and it looks nice.

 

Phase 3- will see us build the interior of the shops with plywood and paneling and then work our way out, the walls and the foam work for the buildings above.

 

In the last phase, Phase 4, we will paint the rest of the set.  I am going to push us to be painting for 3 weeks (all building done in February), because there is a ton of things to paint.